Project Schedule since 2008 – present
With great efforts, high solidarity spirit and determination of Song Giang JSC engineers, contractors, and workers onsite up to the present all items have being executed as scheduled with sound results, as follow:
Installation and execution work:
30 Km of the construction and transportation road has been built, and also 20km the wire has been connected. once the plant comes to operation, this work will be the connection delivering power to the national power grid. As for the water tunnel item, the open excavation was finished; contractor starts to do the digging.
Other items such as dam, penstock, power plant, discharge canal, outdoor distribution station have been finished up to 50%.
In the first season of 2009 BFL starts to deliver equipment to the construction site.
As for the hydraulic-mechanical equipment supplied by Irrigation Equipment JSC, all the equipments were transported onsite. The processing work has been carried out.